Routine documentation and certifications provided by Young Industries
Routine documentation and certifications provided by Young Industries are:
Magnet check 300 Series S/S for material ID
Certified Material Test Reports for material ID
Certificates of Compliance
Run Test Results and Data
Quality Control Documentation Packages
ASME Code Data Forms
I.O.M. Manuals
Customer Supplied Checklists and Inspection Plans
Design calculations (when applicable)
Young Industries uses SolidWorks 3D CAD to reduce the development time for the solids handling equipment. We have standardized on SolidWorks 3D Cad to minimize design cycles, reduce errors, improve communications, and constantly refine product development.
This CAD software can export and import conforming to DXF and IGES formats. We are currently exchanging drawings with customers AutoCAD and export and import to all major CAD packages. We also use AutoCAD to verify transfers to DXF.
SCHEDULE FOR DELIVERY OF ENGINEERING CALCULATIONS, FABRICATION, DRAWINGS, AND OPERATION AND MAINTENANCE MANUALS
Young Industries is prepared to commit to necessary personnel to meet even the most critical fast-track project scheduling. Standard engineering lead times are as follows:
-
Dimensioned equipment arrangement drawings - 5 to 20 working days
-
Dimensioned general arrangement drawings - 25 to 30 working days
-
Piping and instrumentation diagrams - 15 to 20 working days
-
Foundation diagrams and loading requirements - 15 to 20 working days
-
Schematic wiring diagrams - 10 to 20 working days
-
Utility requirements - 15 to 2 5 working days
-
Detailed production schedules - 10 days
-
Complete bill of materials - 30 working days
-
Recommended spare parts - 30 to 45 working days
-
IOM Manuals - 30 to 45 working days